Current Projects:
Local Collector Evaluation and Rehabilitation Project
Owner: Colorado Springs Utilities
Current Contract Value: $40,000,000.00
Project includes installation of various diameters of cured-in-place pipe by Wildcat Civil Services and open cut installation of sanitary sewers by Wildcat Construction. Wildcat Construction has also installed waterline relocations and storm sewer relocations as a part of this project. Also involved in the LCERP project are manhole rehabilitation work and some structural work at creek crossings.
Current completion date: August 2009
Sanitary Sewer Creek Crossings – Major and Minor
Owner: Colorado Springs Utilties
Current Contract Value: Undetermined. Contract Effective Date is January 30, 2009.
Project will include installation and rehabilitation of sanitary sewer creek crossings within the Colorado Springs Utilities system. Projects will include fabrication and installation of structural steel frameworks to support existing aerial creek crossings; bank hardening with installation of rock riprap and/or shotcrete to stabilize creek banks from erosion; and installation of riprap or concrete drop structures to protect existing creek crossings or to modify the channel flow at these locations.
Current completion date: January 2010, with three additional years of renewals
Sewer Rehabilitation Construction Services Program
Owner: Town of Castle Rock.
Current Contract Value: $485,000.00
Project includes on-call services for open cut rehabilitation of sanitary sewer system, including installation of manholes, installation of pipe realignment, and service connections. During 2009, work will include installation of cured-in-place pipe by Wildcat Civil.
Current completion date: December 2009